President Bola Tinubu has given MTN and RCC Construction Company an ultimatum on the completion of the Enugu – Onitsha road, expiring on May 10, 2026.
The president, speaking through his Minister of Works, Senator David Umahi, revealed the ultimatum during a meeting with MTN over the slow funding and execution of the road project categorised under the Infrastructure Development and Refurbishment Investment (Tax Credit) Scheme.
Speaking in the meeting, Umahi reiterated that MTN would be held responsible if the project fails, as speculations of substandard work by the contractor abound. He also noted to RCC that, going forward, the operations of VOP in their must be in accordance with the provisions of the contract and not the personal discretion of the contractor.
The Minister of Works and the former governor of Ebonyi state added that the Federal Ministry of Works is fully committed to a standard delivery of the road project in record time, consistent with the standards set by the ministry under the Tinubu administration.
On the quality of materials being used, Umahi expressed anger at the choice of sand being used by the contractors, stating that the quality is below the approved standard for a federal government contract.
Umahi demanded that the contractors go back to using river sand, which the government paid for, and stop cutting corners. He also pleaded with cement manufacturers to reduce the cost of a bag of cement to N7,000, given the stability of the FX rates in the country.
The evaluation meeting was attended by the Minister of State for Works, Honourable Mohammad Bello Goronyo, the Permanent Secretary of the Federal Ministry of Works, Engineer O O Adebiyi, MTN representatives, the Managing Director of RCC Company Nig Ltd, and his team of employees.
Infoeast View
- The Enugu-Onitsha Expressway, a 110km dual carriageway, is being reconstructed by MTN Nigeria under the Road Infrastructure Tax Credit Scheme.
- The road project is valued at ₦202 billion and is currently facing delays due to MTN’s inconsistent funding.
- Minister David Umahi mandated MTN to pay contractors ₦15 billion monthly to fast-track completion by May 10, 2026, or risk contract termination.
- The road, vital for Southeast Nigeria’s economy, has reached 17% completion