The Abia state government through Ministry of Power and Public Utilities has completed the first phase of the Ohafia Power Restoration Project restoring electricity supply to parts of Ohafia.
The project which remains an Alex Otti initiative has restored power to parts of ohafia which have been off grid and have been in darkness for the last seven years.
Affected communities include Elu Ohafia, Asaga Ohafia and other parts of Ohafia suffering power issues. Key deliverables of the Restoration Project includes
- Completion of a 20km X 33kV High Tension Line from Ihechiowa, Arochukwu to Ebem Injection Substation.
- A 7.5MVA Injection Substation in Ebem Ohafia.
- An 11kV Overhead Power Line to Asaga and FGC Ohafia
- The fixing and completion of Vandalized Transformer Substations in Asaga Ohafia.
The Abia state government advises the general public to be on the lookout for Vandalism and report any such cases to relevant authorities.
The Ohafia Power Restoration Project
The Ohafia Power Restoration Project, also called “Light Up Ohafia,” is the Abia State Government’s effort to bring back public electricity to Ohafia Local Government Area. It is part of the “Light Up Abia Initiative” under Governor Alex Otti.
The Problem
Ohafia communities had been without power for eight years because of vandalism. The blackout paralysed businesses, drained the local economy and pushed young people away. The Ohafia Power restoration project was launched to fix this problem by procuring missing hardware infrastructure and rehabilitating the power infrastructure of the area.
The Abia state government has invested heavily in power infrastructure in the state with the goal of taking the state off the national grid.
The geometric power plant is providing 24 hours electricity to the Aba ringed fenced zone consisting of nine local governments in the state. The geometric power project as well as other independent power projects in the state positions abia as an front-row contender for power sufficient states in Nigeria.